Monday, July 26, 2010

Week 2 update

The Lion Creek project is well underway and progress is ahead of schedule. This week the pilings for both sides of the bridge were drilled and the concrete was poured. J. S. Morris Construction is working to finish welding the wire cages that will be the frame for the bridge abutments. These should be in place and poured with cement sometime next week. The removal of the current creek barrier is also planned to occur next week to make way for the new bridge. Check back next week for more photos.



Workers pouring concrete for the three piles which will support the abutments on each side of the creek.

Silt fencing marks the location of the piles which were recently poured. The new bridge will span the area between the two fences.


J. S. Morris Construction crew welding the joints on the rebar for the wingwalls.













Rebar wingwall structure is in place for one side of the bridge. The other side should be in place shortly as the construction crew prepares to have them filled by the end of the week.