Week 9 Update

This week the final preparations were made to the abutments in anticipation of the installation of the new bridge next week. The roads on either approach to the bridge have been graded. Evans excavating worked to place the final rock around the abutment. Here are a few photos from this week. Please check back for photos of the bridge installation next week.


J.S. Morris Construction making the final additions to the abutments in preparation of the instillation of the new bridge next Tuesday.




Newly graded approaches to the bridge.












The final rock around the abutments is in place.