Friday, August 27, 2010

Week 7 Update

This week the forming of the top of the left bank abutment continued. It should be finished over the weekend in order to begin pouring next Monday or Tuesday. Evans excavating was busy filling in around the right bank abutment to the grade of the new bridge and road. Additionally the placing of large rock around the right bank abutment began. Rock was keyed into with the toe rock that was already in place. Here are a few photos of the projects progress. Please check back for more photos and updates over the next couple weeks.

Evans excavating filling in around the right bank abutment.











Partially formed left bank abutment.












Evans excavating beginning to place large rock around the right bank abutment.












More large rock.


Friday, August 20, 2010

Week 6 Update

This week the forming of the top of the right abutment was finished and poured. Evans excavating was busy filling in around the left bank abutment to allow for Morris Construction to begin forming the top of the abutment on that side. Here are a few photos of the projects progress. Please check back for more photos and updates.


Formed and poured right bank abutment.













Right bank abutment after striping.













Morris Construction crew forming the top of the left bank abutment.












Overview of the project site.

Friday, August 13, 2010

Week 5 Update

This week Evans excavating was busy filling in around the abutments. Large rock was placed along the toe of the slope and then dirt was backfilled in on top. Morris construction worked to frame the top of the abutment on the far bank to be ready to pour early next week. Check back for more photos and updates. Don’t forget to subscribe to the blog if you would like to get email notification of when new posts are up.


Large rock placed along toe of the slope


Dirt being filled in around the abutment.












Forming of the top of the abutment.













Friday, August 6, 2010

Week 4 update

The barrier to fish passage has been removed!!! This week the final pieces of concrete that supported the old bridge were removed from the Lion Creek site. The Morris construction crew worked to form and pour the wing wall for the other side of the creek this week. The initial wing walls for both sides of the bridge are now poured and ready to be filled in to grade. Below are some photos of this week’s activity. Check back next week for more updates.

Evans Excavating working to remove the last piece of the old bridge.











JS Morris Construction working to form the structure around the bridge wing wall in preparation for the concrete pouring.









JS Morris Construction working to pour the concrete for the second wing wall structure.