Friday, August 27, 2010

Week 7 Update

This week the forming of the top of the left bank abutment continued. It should be finished over the weekend in order to begin pouring next Monday or Tuesday. Evans excavating was busy filling in around the right bank abutment to the grade of the new bridge and road. Additionally the placing of large rock around the right bank abutment began. Rock was keyed into with the toe rock that was already in place. Here are a few photos of the projects progress. Please check back for more photos and updates over the next couple weeks.

Evans excavating filling in around the right bank abutment.











Partially formed left bank abutment.












Evans excavating beginning to place large rock around the right bank abutment.












More large rock.