Friday, August 6, 2010

Week 4 update

The barrier to fish passage has been removed!!! This week the final pieces of concrete that supported the old bridge were removed from the Lion Creek site. The Morris construction crew worked to form and pour the wing wall for the other side of the creek this week. The initial wing walls for both sides of the bridge are now poured and ready to be filled in to grade. Below are some photos of this week’s activity. Check back next week for more updates.

Evans Excavating working to remove the last piece of the old bridge.











JS Morris Construction working to form the structure around the bridge wing wall in preparation for the concrete pouring.









JS Morris Construction working to pour the concrete for the second wing wall structure.